Renown Repulse Restoration Group

 
   

 2009 Summary
 
 The following pictures give an idea of the progress made during 2009, more pictures are provided against the individual month sub menus.

 


 
 The cab at No 1 end is shown on the day of the AGM 13th December with the restored drivers dash panels temporarily refitted for display purposes to give an idea of progress todate.

 


 
 This view shows the resistor banks on the top of the electrical cubicle, of note is the fact that at the time of purchase all of this equipment was missing.

 


 
 By the 18th October eight of the overhauled cylinder heads had been refitted to the ex 50008 power unit, five of which are seen in this view.

 


 
2009 also saw the completion of the overhaul of the ETH and Auxiliary Generators for 50030. The work having been undertaken by Bowers Electrical of Heanor.