RRRG new website top logo resized

 

Restoration diary

As one of RRRG's electrical officers I will write about my specialist field as well as general reports of work on site.

Work party report 14th November 2021

Mark, Dave, Jay and I were on site today.

Mark ground off the remains of the anti-slip treads in the gen compartment where they had rotted away or been broken off, in preparation for Ian the welder to fit new ones. He will also fit new ones in places alongside the engine walkways.

Jay and I carried belling out wiring in the electrical cubicle, and we also did the wires to the fuel lift pump / alternator.

Dave had been removing, cleaning and painting more engine room pipework.

Jay took this pic of them at work.

We are working on a much more detailed update of progress on 50030 over the summer of 2021 which we hope to publish soon.

Work party report 8th August 2021
Membership secretary Paul Sturm

Related Posts

Comments

 
No comments yet
Already Registered? Login Here
Guest
Tuesday, 23 April 2024

Captcha Image