Restoration diary

Reports of restoration work on 50029 and 50030.

Announcement of working party dates and details of restoration work carried out at working parties.

Work on site 1st April

I found another 10-12 conduit and pipe clamps that I need for in the generator room. I cleaned these up with wet and dry sandpaper and a wire cut brush, then white spirited them and painted them. Also put another coat of paint on the 40-odd clamps that I did last time I was on site.

I also re-secured 50029’s tarpaulin which was loose and flapping around a bit on one corner.

Dave Rolfe was on site as usual and continued with painting a second coat of paint onto the radiator grilles.  I took a few photos and noted how good they were looking; we will share these here soon.

Continue reading
5972 Hits
0 Comments

Workparty March 25th 2012

Dave was on site all weekend working on cleaning and painting one of the bodyside radiator grilles.



Ian and Pete with some assistance from Dave continued working on the ex-50008 engine replacing some of the head covers.



Steve and Sarah assessed traction motor contactor arc-chutes so spares and paxolin to replace missing parts can be ordered.



The long process of verifying all the cables from the electrical cubicle to equipment in 50029 was started. Each cable was to be tested with a multi-meter to confirm continuity. The first cables checked were those from terminal bar TB6 with blower No1 cables testing out ok. Problems were then encountered as we checked Blower No2 but could get no reading and eventually realised this was because the cables and flexible conduit had been cut about an inch from the connection box.



As it is too difficult to pull any slack through we have decided to dismantle the conduits with a view to reinstalling via a shorter route up the front of the blower negating the need to replace the cables.

Continue reading
5232 Hits
1 Comment

Workparty report for weekend 17th & 18th March.

Tom prepared the cab vestibule at no 2 end for repainting and carried out repairs to ceiling trims. new cab light frames were cut and replacement lights fitted.  Chris unseized the bolts securing the rad fan ducting to the fan motor and freed off the rad fan securing nuts. Doesn't sound much but all are captive and rusted solid so needed considerable work to avoid shearing and drilling out later.

Tim & Dom continued buzzing the surface rust and grime off the brake rigging that had been selected by Chris and Dave for use on the bogie overhauls.  The pile of "to do" components is now virtually nothing and Dom got a very nice facial treatment out of it as well, after which he discovered the shower in the Peak Rail shed is stored unserviceable. Tim took to the bits of rigging Dom had done to clean the areas he couldn't reach, using a drill as opposed to the wire cup brush Dom had. Following this and an unexpected appearance by Chris Bodell the two of them dragged the cleaned-up rigging to join the rest of it in an undercover location.  There they sprayed the pieces with light oil in order to preserve them until we start reassembling the bogies.

I only attended on Sunday, and with the length of the committee meeting, I only had time to fit the last missing shaped copper bar I had made, which goes from the reverser to no.2 traction motor contactor.

Continue reading
4407 Hits
0 Comments

Work party 17-18 March

We will be on site the weekend of 17-18 March to continue restoration work. Anyone in the area is welcome to drop by and say hello although we are planning to have a Committee meeting on Sunday which may take up a good few hours with much to discuss.

Continue reading
4261 Hits
0 Comments

On site activity 25-26 Feb

A good attendance this last weekend, others will contribute their own reports in due course. New volunteer James Andrews arrived on Saturday for his first working party and we were also blessed with the presence of Paul Sturm on an impromptu trip from the Netherlands. Dave Rolfe was the usual permanent fixture on site as Tim and I arrived at about midday on Saturday. Later on Sunday we were joined by Mark Burrows, Ian Kemp and Peter Carter.

Tim, Paul and I concentrated on the continued cleaning of brake rigging equipment where a large stash was extracted from storage:

Dirty brake rigging to be cleaned by Paul Sturm and myself.




;

Although not in the "Chris Thorn" level of restoration skill the wire brushing of these took much elbow grease and many cups of tea and ready meals during the day. The gradual accumulation of brushed parts into a pile for Tim to hone with the smaller drill was quite satisfying:

Brake rigging cleaned with large wire brushes by Paul Sturm and myself, ready for Tim to hone with the smaller drill.




Meanwhile Dave and James had removed one of the adjustable radiator louvres from 50030 with a view to getting the shutters to work again. The linkage was seized utterly solid and heavily rusted. However Paul brushed it up and when Ian arrived on Sunday their combined efforts made for an amazing transformation:

The rusted, seized radiator linkage after brushing up by Paul Sturm and treatment by Ian Kemp with a little used engine oil.




Elsewhere, Dave, obviously heartened by the success on one radiator grille, removed the other one for similar treatment (but did reinstall it before the end of the weekend).

Dave repairing the other opening radiator louvre on 50030 following attention to its companion the previous day.






All in all this was a very productive weekend and I look forward to the next working party.

;

Continue reading
4578 Hits
1 Comment