Restoration diary

Reports of restoration work on 50029 and 50030.

Work party report 6th May 2019

Ian Kemp decided to go to site today as it was a bank holiday and he wasn't working. Wes Needle was available too so I went as well.Quite a productive day, Wes was in No.1 cab again, fitted the windscreen washer control and washer button he'd overhauled, and made a repair to a conduit under the floor. He took away a section of cab panelling to rep...
Continue reading
579 Hits
0 Comments

Compressors update

Compressors update
The main block of a class 50 air compressor, stripped down and partially overhauled.
The motor end of the compressor, as the overhaul progresses.
The compressor crankshaft. Note the surface rust from water ingress.
The electrical machine end of the compressor.
The compressor body. This particular example has suffered water ingress over the years and we will probably use it only for parts to repair another of our compressors as it will be expensive to repair.
The compressor motor field windings overhauled.
Another view of the field windings of the compressor; the electrical end of the machine has been refurbished.
Another view of the refurbished electrical motor field windings of the compressor.
The compressor fan housing.
The compressor motor armature in the process of receiving overhaul.
Air compressor cylinder heads. Note the one on the left shows signs of water damage.
Our medium term goal is to restore 50030 to a state where the Diesel engine can be started up and the locomotive's systems checked. To this end we are concentrating on both the power unit and generators plus the air and vacuum systems. We already have an overhauled vacuum exhauster in secure, heated storage off site and we have a number of compress...
Continue reading
412 Hits
0 Comments

Work party report 10 March 2019

No 1 end cab 50030 with panelling refitted.
Bogie brake adjusters refurbished and ready for refitting to the bogies to replace worn adjusters removed previously.
A good day on Sunday, despite the Arctic wind in the morning. Wes Needle had a very productive day. He started the day by cleaning the debris from under No.1 cab floor on the second man's side. Then, with Dave's help, they checked the operation of the handbrake mechanism under the floor. They found that the pivot nut required tightening and a new s...
Continue reading
1117 Hits
0 Comments

Work party report 17th February 2019

Dave Rolfe, Wes Needle and I were on site on Sunday 17th February. Peak Rail have been reorganising their site during the first weeks of 2019 and opportunities for work parties were also limited by the weather. Dave was removing the brake adjustment parts off the bogies, as he'd identified some that were either worn or where there appeared to be ...
Continue reading
1034 Hits